 |
01/04/2004 |
| |
| |
| |
Commissioning data from design to completion
and beyond is the key to giving end users the buildings they
want, argues Roger Clark*.
ASHRAE president Richard Rooley recently challenged
the building services design profession to come clean about
why so many buildings fail to meet even basic comfort and
energy performance criteria.
“How often do we examine the commissioning
data and compare it with the design brief?” he asked
an audience at the Institution of Mechanical Engineers (IMechE)
last month. An excellent question.
Too often the headlong dash for completion at lowest capital
cost can leave building occupants with long-term running problems,
with the design engineer in an impossible position to properly
influence the process. They know they are designing for an
end user, but during the construction or refurbishment process
it is the developer or contractor who calls the shots. However,
responsibility will come back to the designer if things go
wrong – so we have to be tough, but above all we need
to be better organised.
To win arguments with architects and clients
over system design, engineers need to be sure of their facts
and they need to be flexible. It is important to stress that
commissioning needs to take place at all stages of the design
process from concept, through installation and pre-commissioning
on to balancing, performance testing and final handover. Ideally,
the systems should also be subject to ongoing independent
validation after the occupier takes possession to meet Mr
Rooley’s criteria and ensure that buildings continue
to perform to their design targets throughout their lifetime.
This is particularly important in buildings
that are in use 24 hours a day, seven days a week such as
hospitals, hotels and prisons. We have to ensure they are
set up properly from the outset – you only have one
chance with 24/7 buildings as you can’t shut them down
and start again once they are occupied. That means commissioning
managers should be involved at every stage from concept design
onwards.To make this possible building services designers
should recognise they may have to compromise during discussions
with other members of the project team, but the critical factor
is ensuring that any compromise does not jeopardise the on
going performance of the building.
On PFI projects this should, at least in theory, be an easier
argument to win as the construction team usually has an interest
in the running of the building for 25 years after completion.
‘Keep things simple’ is pretty good
advice for many things in life and holds true for buildings
as does making sure the design objectives are clear and everyone
on the construction team is clear about their areas of responsibility.
Clarity of purpose makes the commissioning engineer’s
job much simpler and helps remove areas of potential conflict.
By ensuring as much testing and commissioning takes place
off site, for example, the services designer gives himself
much more room to maneuver.
Some key rules of thumb include:
- Minimise on site commissioning by using things
like factory calibrated VAV boxes – get as much testing
done in the factory as possible
- Be clear about the designer’s objectives
for the building
- Review the design information to make sure
it is reliable, accurate and complete
- Make sure detailed schedules exist for the
plant and equipment
- Review the controls strategy
- Consider operational efficiency – is
there a better way?
- Develop a strategy and programme for on-going
validation of the services
The long view:
Our industry is very good at developing new ideas and coming
up with clever technical solutions to problems, but we are
not so good at taking the long view and designing for maintenance,
validation and replacement of plant at the end of its life.
Issues like plantroom access and providing lifting beams can
avoid serious problems in the future, but are often overlooked
at design stage.
Architects love to streamline their service
cores, but they can make service and maintenance difficult
as a result. We have to be firm - the chances are that our
first thoughts were right and if we compromise it will be
to the detriment of the building occupants. However, persuading
the architect to change course depends on us being very clear
about our strategy and having a detailed programme to support
our arguments.
Designing spare capacity into the system to allow for changes
in the use of a building and to give occupants the flexibility
to move wards, offices, classrooms and people around and to
accommodate new tenants is another vital area often overlooked.
And it doesn't have to be expensive if you do it at Day One.
Some developers are looking to lower end user expectations
to keep commercial rental costs down, which means they will
go for cheaper alternatives including allowing openable windows
and providing only minimal background lighting. As members
of the design team we should be able to pose the question:
‘Is that the best way – can the building operate
more effectively if we do things differently?’
We need to be sympathetic to the economic pressure
on developers. They are constantly pushing for maximum lettable
area, so any spare space that could be used to accommodate
extra plant for the potential needs of future tenants is often
used up, but with the facts at our fingertips we can make
a case for changes that will benefit the building occupants
in the future.
These economic concerns may actually have a positive effect
on energy use, however. Owners are packing as many people
into their floor space as possible and so are beginning to
see the benefits of bringing energy costs down because of
the relationship between National Insurance contributions
and the Climate Change Levy or Carbon Tax.
The revised Part L of the Building Regulations
is also going to concentrate minds - particularly in highly
glazed buildings. Better control strategies and improved insulation
levels will be required to get the building through the inspection
process.
There is a growing clamour for ‘Building MOT’s’,
which would ensure that, at least once a year, the safety
and business critical processes of a building – like
fire alarms and power back-up systems – are in full
working order.
The legal climate surrounding our projects
is heating up too. Defects liability clauses that put the
onus on contractors to make sure systems work as intended
are becoming more common - another persuasive reason to get
this right.
It is generally accepted that engineering systems,
which are straightforward in commissioning and familiar to
the commissioning engineer can be put to work within the short
timeframe craved by developers. However, if there is complexity
and the systems are prototypes, commissioning may be left
incomplete for several heating and cooling seasons or until
the owners of the building put things right themselves –
perhaps before resorting to litigation or arbitration.
It doesn't’t have to be like this.
If commissioning of services is an integral part of the concept
design, we can ensure buildings work as intended and that
the commissioning data meets the performance levels set in
the design brief – as Mr Rooley would expect.
We do design wonderful systems, but if they
are not tested properly and commissioned, then they will not
work as intended and the design will be a failure.
Sometimes it takes years to fathom why systems are not working
properly and because of the time pressures to finish buildings,
it is often difficult to complete testing, but a proper commissioning
strategy means testing can go on at all stages of the project
and does not need to be left to the end.
We need to think about design for commissioning and testing,
to record the process and then ensure the documents are kept
safely somewhere on site so that the occupants can continue
to run the building as intended. By keeping this documentation
up-to-date, building users have a full record of the current
status of the building rather than an historic record of how
it was meant to be.
At the end of the day, being too clever or complicated
doesn’t help anyone – least of all the end user.
It is designing something that works and will continue to
work that matters.
*Roger Clark is Group Director of The Commtech
Group.
Breakfield
The Ullswater Business Park
Coulsdon
Surrey
CR5 2HS
Tel: 020 8668 0312
Fax. 020 8668 0975
enquiry@commtechgroup.co.uk
Copyright 2004 Commtech Group -
by wickedweb.co.uk
|